Het OWA, het open archief van het Waterbouwkundig Laboratorium heeft tot doel alle vrij toegankelijke onderzoeksresultaten van dit instituut in digitale vorm aan te bieden. Op die manier wil het de zichtbaarheid, verspreiding en gebruik van deze onderzoeksresultaten, alsook de wetenschappelijke communicatie maximaal bevorderen.
Dit archief wordt uitgebouwd en beheerd volgens de principes van de Open Access Movement, en het daaruit ontstane Open Archives Initiative.
Basisinformatie over ‘Open Access to scholarly information'.
one publication added to basket [285342] |
Optimised scheduling for weather sensitive offshore construction projects
In: Omega-International Journal of Management Science. PERGAMON-ELSEVIER SCIENCE LTD: Oxford. ISSN 0305-0483, meer
| |
Author keywords |
Offshore construction; Weather simulation; Stochastic scheduling;Project scheduling |
Auteurs | | Top |
- Kerkhove, L.-P., meer
- Vanhoucke, M.
|
|
|
Abstract |
The significant lead times and costs associated with materials and equipment in combination with intrinsic and weather related variability render the planning of offshore construction projects highly complex. Moreover, the way in which scarce resources are managed has a profound impact on both the cost and the completion date of a project. Hence, schedule quality is of paramount importance to the profitability of the project. A prerequisite to the creation of good schedules is the accuracy of the procedure used to estimate the project outcome when a given schedule is used. Because of the systematic influence of weather conditions, traditional Monte Carlo simulations fail to produce a reliable estimate of the project outcomes. Hence, the first objective of this research is to improve the accuracy of the project simulation by creating a procedure which includes both uncertainty related to the activities and an integrated model of the weather conditions. The weather component has been designed to create realistically correlated wind- and weather conditions for operationally relevant time intervals. The second objective of this research is to optimise the project planning itself by using both general meta-heuristic optimisation approaches and dedicated heuristics which have been specifically designed for the problem at hand. The performance of these heuristics is judged by the expected net present value of the project. The approach presented in this paper is tested on real data from the construction of an offshore wind farm off the Belgian coast and weather data gathered by the Flanders Marine Institute using measuring poles in the North Sea. |